Question: 1 pts D Question 3 ments A project's critical path is ABDE. The project activity information in weeks) are as follows. Assume the project finish

1 pts D Question 3 ments A project's critical
1 pts D Question 3 ments A project's critical path is ABDE. The project activity information in weeks) are as follows. Assume the project finish time follows a normal distribution, nts A B D E F to Course Activity Expected FT Variance 6 4 5 8 9 4 1 3 2 3 9 2 If the project deadline is set to be 23 weeks, then what the 2-value to determine the probability that the project will be finished before the given deadline? Numbers only, Keep 3-decimal if not exact either round up or down is ok