Question: A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume. the project finish time follows a normal distribution. If

A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume. the project finish time follows a normal distribution. If the project deadline is set to be 22 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline? Numbers only. Keep 3-decimal if not exact, either round up or down is ok, A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume. the project finish time follows a normal distribution. If the project deadline is set to be 22 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline? Numbers only. Keep 3-decimal if not exact, either round up or down is ok
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts