Question: 1 ptsA project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical
1 ptsA project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 315 days with a project variance of 100, what is the probability that the project will take 325 days or more to complete?0.840.0131.700.16Near zero