Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 60

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete? O A. 0.8413 OB. 0.0126 OC. 0.1587 OD near Zero O E. 2.14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!