Question: 1 . Question 1 Your quality management plan uses a panel of experienced users to preview new features. You find the benefit of this preview

1.
Question 1
Your quality management plan uses a panel of experienced users to preview new features. You find the benefit of this preview process is that it reduces the amount of time and money spent to implement features that users are not eager to use. Which of the following describes this benefit of your quality management plan?
1 point
Increased collaboration
Quality standards
Decreased overhead
Delivering a quality product
2.
Question 2
Which of the following are common resources for determining quality standards? Select all that apply.
1 point
Industry research
Business case documents
Corporate vision statements
Profit and loss statements
3.
Question 3
What is the purpose of quality assurance in quality management?
1 point
To evaluate and measure how well your project meets its goals
To determine quality standards for your project
To maintain current processes
To decrease overhead
4.
Question 4
There are two main categories of evaluation questions: Questions that ask how you can make improvements and questions that help you measure and compare outcomes. Which of the following questions intends to help you make improvements?
1 point
What were the results of this evaluation?
What are the most common participant reactions?
What are the costs and benefits?
Should we continue?
5.
Question 5
You are evaluating a customer experience initiative that you manage for an online clothing store. Which of the following evaluation indicators would answer this evaluation question: Are customers paying attention to our email newsletters?
1 point
Customers are 47% more likely to recommend your store to a friend.
Customers redeem store coupons 25% more often.
The store has increased the advertising budget by 25%.
Customers are 35% more likely to recommend your store to a friend.
6.
Question 6
You are creating a survey about the implementation of a new tool in your company. You include the question How many times have you used the new tool this week? The answer options are zero times,1-2 times,3-4 times, and more than 4 times. What type of survey question are you asking?
1 point
An open-ended question
A close-ended scaled question
A close-ended multiple choice question
A close-ended true/false question
7.
Question 7
In addition to a full-summary report, what are two other ways that you can present information in a timely manner during a presentation? Select all that apply.
1 point
By using vague and general terms
By using a summary sheet
By using jargon and technical terms
By using a slide-based presentation
8.
Question 8
As a project manager, what is your role during a retrospective? Select all that apply.
1 point
Stay silent and let team members lead the discussion
Identify details to include in the retrospective document
Ensure all team members feel included
Manage the tone of the discussion
9.
Question 9
As a project manager, you are leading a project retrospective. You start the meeting by reminding the team that no stakeholders or customers are involved in this meeting. What technique are you using to encourage participation in the retrospective?
1 point
Pose a question each participant can answer
Create a safe environment
Review the project timeline
Model team participation
10.
Question 10
In the context of a retrospective, what term best refers to responsibility for decisions associated with a project or task?
1 point
Blame
Participation
Accountability
Management

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!