Question: 1. Resource allocation problem. The following project information includes the project activities, activity durations and workers assigned to each activity (30 points). Activity IPA Duration

1. Resource allocation problem. The following project information includes the project activities, activity durations and workers assigned to each activity (30 points). Activity IPA Duration Workers A 5 2 B C A D A, B 5 3 E C.D 2 2 a) Calculate the aggregate number of workers per day (10 pts) Bar Chart for Project Activities A B C D F DAYS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 LABORERS critical non-critical activity activity float