Question: The following project information includes the project activities, activity durations and workers assigned to each activity Activity IPA Duration Workers A ---- 5 2 B
- The following project information includes the project activities, activity durations and workers assigned to each activity
| Activity | IPA | Duration | Workers |
| A | ---- | 5 | 2 |
| B | ---- | 7 | 4 |
| C | A | 3 | 3 |
| D | A, B | 5 | 3 |
| E | C,D | 2 | 2 |
- Calculate the aggregate number of workers per day
| Bar Chart for Project Activities | ||||||||||||||
| A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| B |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| C |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| E |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| DAYS | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| LABORERS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| critical activity |
| non-critical activity |
| float | |||||||||
- Draw a resource usage profile below using an Early Start schedule.
- Assuming that your company only has 6 workers available and wants to minimize any unnecessary fluctuations in their schedule, level the resources for the project and show the new resource usage profile below.
- What activities were changed and how were they changed to accomplish the new schedule shown above?