Question: 1. (SHOW YOUR COMPLETE WORK) An activity on a PERT network has an optimistic time of 6 days, a most likely time of 11 days,
1.
(SHOW YOUR COMPLETE WORK)
An activity on a PERT network has an optimistic time
of 6 days, a most likely time of 11 days, and a pessimistic time of 25 days. Find its EXPECTED
TIME, VARIANCE, and STANDARD DEVIATION.
Use appropriate units/labels in your
answers
.