Question: An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of

An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of 15 days. Find its STANDARD DEVIATION.

Group of answer choices

2.5 days

1 day

2 days

1.5 days

0.5 day