Question: 1. Six jobs are to be processed a two step operation. What is the sequence of jobs? 2. How many weeks will it take to

1. Six jobs are to be processed a two step

1. Six jobs are to be processed a two step

1. Six jobs are to be processed a two step operation. What is the sequence of jobs? 2. How many weeks will it take to get the jobs done? 3. Why is job E assigned to the first position? 4. Why is job F assigned to the sixth position? Module/submodel: Scheduling Problem title: (untitled) Results Nakespan =35 Sequence of jobs B,D,C,A,B,F Johnson's Method Steps