Question: 1. Smallest cycle (iteration) in Agile project management is called a. Prince b. Lean c. Sprint d. Waterfall 2. The most stable and dynamic PM

1. Smallest cycle (iteration) in Agile project management is called
a. Prince
b. Lean
c. Sprint
d. Waterfall
2. The most stable and dynamic PM methodologies are: (choose as many applies)
a. Prince2
b. Kanban
c. PMBOK
d. Scrum
3. Which of the following methodologies are similar to each other? Make two sets.
a. Prince2
b. Scrum 1 ______________ & ________________
c. Lean
d. Kanban 2 ______________ & _________________
e. PMBOK
f. Agile
4. PMBOK is a universal standard of waterfall methodology True or False
5. What is NOT a disadvantage of an outsourcing work project?
A. Coordination breakdowns
B. Flexibility
C. Interpersonal conflict
D. Security issues
6. Which one of the below is not favoring Partnering approach?
A. Existence of common goals
B. High costs of the adversarial approach
C. Low cost of the adversarial approach
D. Shared benefits of the collaborative approach
7. The transferring of business functions or processes to other companies has traditionally been known as
A. Subcontracting.
B. Partnering.
C. Joint venture.
D. Outsourcing.
Advantages of outsourcing project work may likely include all of the following EXCEPT
A. Shortened project duration.
B. Reduced costs.
C. Higher level of expertise.
D. Reduced conflict.
8. Disadvantages of outsourcing project work may likely include all of the following EXCEPT
A. Increased conflict.
B. Coordination breakdowns.
C. Increased costs.
D. Loss of control.
9. Key practices in the partnering approach to managing contracted relationships include
A. Single project contracting.
B. Risk being transferred to the other party.
C. Access to each other's organizational resources.
D. Structured communications.
10. Which one is NOT a communication strategy with outsourcers?
A. Recognize cultural difference
B. Choose the right word
C. Confirm your requirements
D. Considering them a stakeholder

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!