Question: 1 . Suppose we use the earliest due date ( EDD ) algorithm to schedule three jobs ( recall that each job has a deadline
Suppose we use the earliest due date EDD algorithm to schedule three jobs recall that each job has a deadline and a processing time Assume that the EDD algorithm produces the schedule Job then Job then Job If we use this EDD schedule and Job is late, then Job is also late marks
Suppose a project has activities Activity A to J The path A B C D F J is days, the path of A B C D E J is days and Path A B C D G J is days. If the activity E is crashed by days, then the overall duration of the project will decrease by days. marks
Suppose a project has four critical activities. The project manager only needs to crash one critical activity to reduce the overall duration of the project marks