Question: 1. The average cost per unit is $73.15 at the best operating level. When the output is higher, the unit will be what? a. higher
1. The average cost per unit is $73.15 at the best operating level. When the output is higher, the unit will be what?
a. higher
b. could be higher, lower, pr the same
c. the same
d. lower
e. could be higher or lower
2. The cumulative lead time in a product structure is
a. the longest of the time paths in the product structure tree for an end time
b. lead time less safety time
c. the sum of the lead time for all the components
d. the number of time buckets used in the MRP
e. the sum of the lead time and the safety time