Question: 1- The critical activities must form a continuous path from project beginning to project end, this chain of critical activities is called: Select one: a.

1- The critical activities must form a continuous path from project beginning to project end, this chain of critical activities is called:

Select one:

a.

Critical path

b.

Management path

c.

Risk management

2- It is the schedule variance expressed in percentage terms. SPI = EV/PV. For example, SPI = 0.50 means the project is 50% behind schedule.

Select one:

a.

Schedule Variance (SV)

b.

Schedule Cost Variance (SCV)

c.

Schedule Performance Index (SPI)

3-Type of planning occurring at the corporate level for achieving the vision of the organization is termed as:

Select one:

a.

Technical planning

b.

Strategic planning

c.

Operational planning

4- A set of activities directed at an organizations resources (human, financial, physical and informational) with the aim of achieving organizational goals in an efficient and effective manner.

Select one:

a.

Engineering

b.

Risk management

c.

Management

5- Type of planning where the process of deciding in advance of what is to be done to achieve the tactical objectives of the business is called:

Select one:

a.

Technical planning

b.

Operational planning

c.

Strategic planning

6-A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a projects success.

Select one:

a.

Project Management

b.

Engineering Management

c.

Risk Management

7-The management process includes (Planning, Controlling, Leading and Organizing).

Select one:

True

False

8-Project closure involves monitoring, controlling, closure and review activities.

Select one:

True

False

9-Project Performance - It is a process showing relationship of activities and determining of the project time and the timing of the activities comprising the project.

Select one:

True

False

10-Relies information from similar projects to determine the activity duration; needs historical data is Parametric Estimation.

Select one:

True

False

11-McGregor and Hersey & Blanchard both are Styles of Leadership

Select one:

True

False

12-Initiation phase involves project definition, project constraints activities.

Select one:

True

False

13-Once the project is underway, the schedule may need to be revised based on initial progress. This ensures (1) cost estimates and (2) time constraints are maintained at a specific level of quality and scope.

Select one:

True

False

14-In (AON), the earliest finish of an activity is the earliest possible time that it can be completed and is determined by adding that activity's duration to its early start time

Select one:

True

False

plzz answer only select the answeer.. as possible plzz fast

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!