Question: 1. The Earliest Start Time for task J is: 2. The Latest Start Time for task B is: 3. The Critical Path for this project
1. The Earliest Start Time for task J is:
2. The Latest Start Time for task B is: 3. The Critical Path for this project is:
4. What is the expected completion time for the project?
5. You can accomplish any one of the following at an additional cost of $1,500:
(1) Reduce task E by two days.
(2) Reduce task C by two days.
(3) Reduce task G by two days.
If you save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose?
A. Reduce task E by two days.
B. Reduce task G by two days.
C. None of the other options.
D. Reduce task C by two days.
6. What is the possibility that the project will take less than 30 days to complete?
For questions 2 to 10 , please consider the following problem: A construction project is broken down into the following 11 tasks