Question: 1 . The following table represents a plan for a project: begin { tabular } { | l | l | l | l

1. The following table represents a plan for a project:
\begin{tabular}{|l|l|l|l|l|}
\hline \begin{tabular}{l}
Job \\
Num
\end{tabular} & \begin{tabular}{l}
Predecessor \\
Jobs
\end{tabular} & a & m & b \\
\hline 1 & & 2 & 3 & 4\\
\hline 2 & 1 & 1 & 2 & 3\\
\hline 3 & 1 & 4 & 5 & 12\\
\hline 4 & 1 & 3 & 4 & 11\\
\hline 5 & 2 & 1 & 3 & 5\\
\hline 6 & 3 & 1 & 2 & 3\\
\hline 7 & 4 & 1 & 8 & 9\\
\hline 8 & 5,6 & 2 & 4 & 6\\
\hline 9 & 8 & 2 & 4 & 12\\
\hline 10 & 7 & 3 & 4 & 5\\
\hline 11 & 9,10 & 5 & 7 & 8\\
\hline
\end{tabular}
a. Construct the appropriate network diagram.
b. Indicate the critical path.
c. What is the expected completion time for the project?
d. You can accomplish any one of the following at an additional cost of \(\$ 1,500\) :
1. Reduce job 5 by two days.
2. Reduce job 3 by two days.
3. Reduce job 7 by two days.
If you save \(\$ 1,000\) for each day that the earliest completion time is reduced, which action, if any, would you choose?
e. What is the probability that the project will take more than 28 days to complete?
1 . The following table represents a plan for a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!