Question: The following table represents a plan for a project in days: (a) Construct the appropriate network diagram. (1 point) 1 Job # Immediate Predecessors 1

 The following table represents a plan for a project in days:

The following table represents a plan for a project in days: (a) Construct the appropriate network diagram. (1 point) 1 Job # Immediate Predecessors 1 Optimistic 2 2 1 1 1 2 3 4 5 6 7 8 9 3 3 2 3 Most Likely 3 4 2 5 7 3 5 8 4 2 3 4 5 6 7 8,9,10 Pessimistic 5 5 3 12 12 4 6 10 5 7 11 4 3 5 10 11 6 10 7 (b) Calculate expected times and variances of all activities (assuming a Beta distribution). (2 points) (c) List all paths of the network and their expected durations and variances. (3 points) (d) What is the expected and standard deviation of the completion time for the project? (1 point) (e) What is the probability that the project will take more than 30 days to complete? (1 point) The following table represents a plan for a project in days: (a) Construct the appropriate network diagram. (1 point) 1 Job # Immediate Predecessors 1 Optimistic 2 2 1 1 1 2 3 4 5 6 7 8 9 3 3 2 3 Most Likely 3 4 2 5 7 3 5 8 4 2 3 4 5 6 7 8,9,10 Pessimistic 5 5 3 12 12 4 6 10 5 7 11 4 3 5 10 11 6 10 7 (b) Calculate expected times and variances of all activities (assuming a Beta distribution). (2 points) (c) List all paths of the network and their expected durations and variances. (3 points) (d) What is the expected and standard deviation of the completion time for the project? (1 point) (e) What is the probability that the project will take more than 30 days to complete? (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!