Question: 1.) The LS time for an activity in a network is the earliest time that an activity can start without violation of precedence requirements. latest
1.) The LS time for an activity in a network is the
| earliest time that an activity can start without violation of precedence requirements. | ||
| latest time that an activity can be started without delaying the entire project. | ||
| None of these. | ||
| latest time that an activity can be finished without delaying the entire project. |
2.) You have determined the following for a given project:
Expected completion time of the project = 40 weeks
Standard deviation of project completion time = 8
What is the probability of completing the project in more than 44 weeks?
Report your answer as a decimal and take it to four places.
3.) You have determined the following for a given project:
Expected completion time of the project = 26 weeks
Standard deviation of project completion time = 8
What is the probability of completing the project in more than 32 weeks?
Report your answer as a decimal and take it to four places.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts