Question: Given is a Project with network diagram and activity times as shown below. Activity A Time (wks) 3 B 7 Start C 4 D a)
Given is a Project with network diagram and activity times as shown below. Activity A Time (wks) 3 B 7 Start C 4 D a) The Earliest Start (ES) time of Activity I = Blank 1 weeks c) The Slack time of Activity C = Blank 3 weeks 7 b) The Latest Start (LS) time of Activity B = Blank 2 weeks d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks f) The Project Completion time - Blank 6 weeks e) The Latest Finish (LF) time of Activity B = Blank 5 weeks E 6 C F 13 H G 7 H 5 I 6 J 5
Given is a Projest with nctwork diagram and activity times as shown below: a) The Earliest Start (ES) time of Actrvity I = Hank I weeks b) Tbe Latest Start (LS) time of Actrvity B = Hank 2 weeks c) The Slack time of Activity C= Blask 3 wecks d) The Farbest Finish (EF) time of Activify H= Blank 4 wocks c) The Latent Fansh (IF) time of Astivity H = Flank 5 wseks f) The Project Completion nume = Blank 6 wecks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock