Question: 1. The process lead time is: a. The time for the individual operations within the process b. The total time of the process from start

1. The process lead time is:

a. The time for the individual operations within the process

b. The total time of the process from start to the end

c. The total number of units produced

d. The amount of variation within the process

2. The value stream map will show two types of flow:

a. The information and the material flow

b. The customer information and the production information

c. The material and coordination flows

d. The information and process flows

3. The data box within a VSM shows:

a. All the non-value-added activities

b. Only what the customer wants

c. Key metrics related to the flow

d. Only the information flow related

4. The five key lean principles are (in order):

a. Value Value Stream Customer orders Customer Pulling and Perfection

b. VOC Value Stream Flow Customer Pulling and Perfection

C. Value Value Stream Flow Customer Pulling and Perfection

d. Value - Value Stream Flow Customer Pulling and Perfection

5. There are different types of waste as defined by the lean thinking organizational model:

a. There are 7 types of waste

b. There are 7+1 types of waste

c. There is only one type of waste

d. There are non value added activities and value-added activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!