Question: 1 The project completion time is -------, with a normal cost of --------. * 25 days; $1,545 18 days; $1,295 15 weeks; $2,300 30 days;

1 The project completion time is -------, with a normal cost of --------. *
25 days; $1,545
18 days; $1,295
15 weeks; $2,300
30 days; $3,870
None of the answers
2 The Crashing Cost/Activity for activity "C" is *
$100
$200
$50
$110
None of the answers
3 The "number of activity crashing" for activity "E" is *
2 weeks
2 days
1 week
1 day
None of the answers
4 To crash the project by 1 day we choose activity _______ at an additional crashing cost of __________ *
A; $25
C; $50
G; $150
C, $100
None of the answers
5 The new "project cost" is equal to: *
$1,320
$1,345
$2,560
$1,395
None of the answers
6 To crash the project by an additional day, we choose activity _______ at an additional crashing cost of ______ *
A; $25
G; $150
B, $110
C; $50
None of the answers
7 The resulting "project cost" is: *
$1,395
$2,670
$1,370
$4,170
None of the answers
8 Crashing the project by 2 days results in: *
One critical path " B E - G H "
One critical path " A - C - F H "
Two alternative critical paths which are " B E - G H " & "A - C - H"
Two alternative critical paths which are "A - C - F - H" & " A - D - F H "
None of the answers
9 To crash the project by a third day we choose ________ at an additional cost of : *
E; $75
A & B; $180
A; $80
B; $140
None of the answers
10 to crash the project by a 4th day we choose ________ at an additional cost of *
F, $100
H, $150
E, $75
A, $80
None of the answers
Activity Predecessor A B D E F G H A A B C, D E F, G Normal Time 3 5 4 2 4 9 4 2 Crashing Time 2 4 2 1 3 8 3 1 Normal Cost $ 100 220 100 300 225 150 100 100 Crashing Cost $ 180 330 200 450 300 250 300 250Step by Step Solution