Question: 1 The project completion time is -------, with a normal cost of --------. * 25 days; $1,545 18 days; $1,295 15 weeks; $2,300 30 days;

1 The project completion time is -------, with a

1 The project completion time is -------, with a normal cost of --------. *

25 days; $1,545

18 days; $1,295

15 weeks; $2,300

30 days; $3,870

None of the answers

2 The Crashing Cost/Activity for activity "C" is *

$100

$200

$50

$110

None of the answers

3 The "number of activity crashing" for activity "E" is *

2 weeks

2 days

1 week

1 day

None of the answers

4 To crash the project by 1 day we choose activity _______ at an additional crashing cost of __________ *

A; $25

C; $50

G; $150

C, $100

None of the answers

5 The new "project cost" is equal to: *

$1,320

$1,345

$2,560

$1,395

None of the answers

6 To crash the project by an additional day, we choose activity _______ at an additional crashing cost of ______ *

A; $25

G; $150

B, $110

C; $50

None of the answers

7 The resulting "project cost" is: *

$1,395

$2,670

$1,370

$4,170

None of the answers

8 Crashing the project by 2 days results in: *

One critical path " B E - G H "

One critical path " A - C - F H "

Two alternative critical paths which are " B E - G H " & "A - C - H"

Two alternative critical paths which are "A - C - F - H" & " A - D - F H "

None of the answers

9 To crash the project by a third day we choose ________ at an additional cost of : *

E; $75

A & B; $180

A; $80

B; $140

None of the answers

10 to crash the project by a 4th day we choose ________ at an additional cost of *

F, $100

H, $150

E, $75

A, $80

None of the answers

Activity Predecessor A B D E F G H A A B C, D E F, G Normal Time 3 5 4 2 4 9 4 2 Crashing Time 2 4 2 1 3 8 3 1 Normal Cost $ 100 220 100 300 225 150 100 100 Crashing Cost $ 180 330 200 450 300 250 300 250

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!