Question: 1. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of: Group

1. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of:

Group of answer choices

Completion in the shortest possible time frame

Customer satisfaction

Having lower cost than competitor

Making a maximum profit

2. Resource leveling will generally:

Group of answer choices

Reduce resources to the lowest skill that is possible

Increase the total time necessary to complete all the tasks

Reduce the time needed to do the project

Reduce the over utilization of resources

3.You are the Project Manager of a car manufacturing company. As part of Quality Control you decide to check only 5% of the cars generated for environmental check. Which technique are you using?

Group of answer choices

Statistical Selection

Pareto Diagram

Control Charts

4.Deflection or transfer of a risk to another party is part of which of the following risk response categories?

Group of answer choices

Acceptance

Mitigation

Analysis

Avoidance

5. Doing activities in parallel that would normally be done sequentially in order to achieve project objectives or to deal with resource allocation problems is called

Group of answer choices

Objectives management

Crashing

Fast Tracking

Accelerating

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!