Question: 1. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of: Group
1. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of:
Group of answer choices
Completion in the shortest possible time frame
Customer satisfaction
Having lower cost than competitor
Making a maximum profit
2. Resource leveling will generally:
Group of answer choices
Reduce resources to the lowest skill that is possible
Increase the total time necessary to complete all the tasks
Reduce the time needed to do the project
Reduce the over utilization of resources
3.You are the Project Manager of a car manufacturing company. As part of Quality Control you decide to check only 5% of the cars generated for environmental check. Which technique are you using?
Group of answer choices
Statistical Selection
Pareto Diagram
Control Charts
4.Deflection or transfer of a risk to another party is part of which of the following risk response categories?
Group of answer choices
Acceptance
Mitigation
Analysis
Avoidance
5. Doing activities in parallel that would normally be done sequentially in order to achieve project objectives or to deal with resource allocation problems is called
Group of answer choices
Objectives management
Crashing
Fast Tracking
Accelerating