Question: 1. The Scrum approach for managing iterative development involves and/or incorporates which of these? Select ALL that apply. Select one or more: a. planning and
1. The Scrum approach for managing iterative development involves and/or incorporates which of these? Select ALL that apply.
Select one or more:
a. planning and architectural design
b. daily team meetings
c. software developer team of at least 15 members
d. multiple sprint cycles
e. sprint cycle of 6 to 8 weeks duration
2. Review these statements about software. Select ALL statements that are TRUE.
Select one or more:
a. Maintaining software falls outside of software engineering.
b. Software is a computer program that is developed for the general marketplace not for a specific customer.
c. Software engineering is just one aspect of system engineering.
d. Software engineering is concerned with all aspects and phases of software production.
3. True or False: There are no universal software engineering methods that are suitable for all systems, developers, or customers.