Question: 1.) The slack for Activity C will equal _________ if it is on the critical path. 0 EF minus ES none of these LF minus
1.)
The slack for Activity C will equal _________ if it is on the critical path.
| 0 | ||
| EF minus ES | ||
| none of these | ||
| LF minus EF |
2.) Using the chart of activity data provided below, what is expected standard deviation for activity C?
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 9 | 12 | 21 |
| B | 14 | 21 | 23 |
| C | 10 | 15 | 25 |
3.) What is the length (in days) of the critical path for the network described by:
| Activity | Immediate Predecessor | Time (days) |
| A | -- | 10 |
| B | A | 4 |
| C | A | 6 |
| D | B | 7 |
| E | C | 6 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
