Question: 1.) The slack for Activity C will equal _________ if it is on the critical path. 0 EF minus ES none of these LF minus

1.)

The slack for Activity C will equal _________ if it is on the critical path.

0

EF minus ES

none of these

LF minus EF

2.) Using the chart of activity data provided below, what is expected standard deviation for activity C?

Activity Optimistic Most Likely Pessimistic
A 9 12 21
B 14 21 23
C 10 15 25

3.) What is the length (in days) of the critical path for the network described by:

Activity Immediate Predecessor Time (days)
A -- 10
B A 4
C A 6
D B 7
E C 6