Question: Question 1 ( 2 . 5 points ) Listen The earliest finish time for the final activity is the project duration. Question 1 options: a

Question 1(2.5 points)
Listen
The earliest finish time for the final activity is the project duration.
Question 1 options:
a) True
b) False
Question 2(2.5 points)
Listen
Activities with zero slack
Question 2 options:
a) have no predecessors.
b) must be completed first.
c) can be delayed.
d) lie on a critical path.
Question 3(2.5 points)
Listen
The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
Question 3 options:
a) True
b) False
Question 4(2.5 points)
Listen
An activity has an Optimistic activity time of 3 days, a Most Probable activity time of 6 days, and a Pessimistic activity time of 9 days. The average or expected time for the activity is
Question 4 options:
a)3
b)5
c)6
d)9
Question 5(2.5 points)
Listen
An activity in a project network cannot begin until all of the activities leading into that activity have been completed.
Question 5 options:
a) True
b) False
Question 6(2.5 points)
Listen
The path in a project network with the average duration is the critical path.
Question 6 options:
a) True
b) False
Question 7(2.5 points)
Listen
Activities K, M and S immediately follow activity H, and their latest start times are 14,18, and 11. The latest finish time for activity H
Question 7 options:
a) is 11.
b) is 14.
c) is 18.
d) cannot be determined.
Question 8(2.5 points)
Listen
The slack of an activity is the difference between the latest finish and the earliest finish times.
Question 8 options:
a) True
b) False
Question 9(2.5 points)
Listen
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,15, and 10, then the earliest start time for W
Question 9 options:
a) is 10.
b) is 12.
c) is 15.
d) cannot be determined.
Question 10(2.5 points)
Listen
Non-critical activities are distinguished by the presence of
Question 10 options:
a) idle resources.
b) zero slack.
c) wasted time.
d) slack.
Question 11(2.5 points)
Listen
When making a backward pass through a project network, you must start at the finish node.
Question 11 options:
a) True
b) False
Question 12(2.5 points)
Listen
Which of the following is always true about a critical activity?
Question 12 options:
a) LF = LS.
b) LS = EF.
c) EF = ES.
d) ES = LS.
Question 13(2.5 points)
Listen
All activities on a critical path have zero slack time.
Question 13 options:
a) True
b) False
Question 14(2.5 points)
Listen
The critical path
Question 14 options:
a) is the shortest path.
b) is any path that goes from the starting node to the completion node.
c) is the longest path.
d) is a combination of all paths.
Question 15(2.5 points)
Listen
One of PERT's bold assumptions is that
Question 15 options:
a) individual activity times are constant.
b) individual activity times are uncertain.
c) individual activity times can be added together.
d) individual activity times are dependent of each other.
Question 16(2.5 points)
Listen
The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project.
Question 16 options:
a) True
b) False
Question 17(2.5 points)
Listen
Arcs in a project network indicate
Question 17 options:
a) completion times.
b) precedence relationships.
c) durations.
d) the critical path.
Question 18(2.5 points)
Listen
A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.
Question 18 options:
a) True
b) False
Question 19(2.5 points)
Listen
Arcs in a project network indicate
Question 19 options:
a) completion times.
b) the critical path.
c) precedence relationships.
d) activities
Question 20(2.5 points)
Listen
The purpose of the forward pass in the Critical Path Method technique is to
Question 20 options:
a) Review each of the precedence relationships in the activity network.
b) To calculate the slack time within each node on the activity network.
c) To determine the earliest time each activity can start and finish.
d) To determine the latest time each activity can start and finish.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!