Question: 1. There is no difference between the CPM and PERT technique when it comes to how the activity time for each node is determined. T/F
1. There is no difference between the CPM and PERT technique when it comes to how the activity time for each node is determined. T/F
2. In Project Management, it is important to monitor activities that are not on the critical path. T/F
3. Which if the following statements regarding Critical Path Analysis is true?
| a. The shortest of all paths through the network is the critical path. |
| b. Some activities on the critical path may have slack. |
| c. There cannot be more than one critical path in the network |
| d. The longest of all paths through the network is the critical path |