Question: 1. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88.What is the probability
1. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88.What is the probability of finishing between 24 and 23 weeks? Express as a percentage with one decimal place (i.e. 65.2).
2. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88.What timeline would yield a 60% probability of completing? Express as a number of weeks with two decimal places.