Question: a. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88. The deadline for
a. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88. The deadline for the project is 28 weeks. What is the probability of finishing on time? Express as a percentage with one decimal place (i.e. 65.2).
b. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88.The deadline for the project is 28 weeks. What is the probability of finishing late? Express as a percentage with one decimal place (i.e. 65.2).
c. This question relates to a new project. It has an expected completion time of 25 weeks and a variance of 3.88.What is the probability of finishing the project in 24 weeks? Express as a percentage with one decimal place (i.e. 65.2).