Question: 1. Time required for the 7th unit = __ hours 2. Time required for the 8th unit = ___ hours Please answer both parts ^
1. Time required for the 7th unit = __ hours
2. Time required for the 8th unit = ___ hours
Please answer both parts ^
Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 20,000 hours to produce. Using an 85% learning curve and a $30-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = 17002.31 hours (round your response to the nearest whole number). Cost of the sixth unit = 510069 dollars (round your response to the nearest whole number). Time required for the seventh unit = hours (round your response to the nearest whole number)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts