Question: 1. Time required for the 7th unit = __ hours 2. Time required for the 8th unit = ___ hours Please answer both parts ^

1. Time required for the 7th unit = __ hours 2.1. Time required for the 7th unit = __ hours

2. Time required for the 8th unit = ___ hours

Please answer both parts ^

Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 20,000 hours to produce. Using an 85% learning curve and a $30-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = 17002.31 hours (round your response to the nearest whole number). Cost of the sixth unit = 510069 dollars (round your response to the nearest whole number). Time required for the seventh unit = hours (round your response to the nearest whole number)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!