Question: 1- To manage capacity in the Intermediate range (usually 3 to 36 months) which of the options cannot be used a. Subcontract b. Add Facilities
1- To manage capacity in the Intermediate range (usually 3 to 36 months) which of the options cannot be used a. Subcontract b. Add Facilities c. Add Equipment d. Add Shifts
2- A company producing special handbags has five workstations (A, B, C, D and E). C and D does the same operation in parallel. The per unit times at each workstations are: A takes 35 seconds, B takes 40 seconds, C takes 30 seconds, D takes 30 seconds and finally E takes 25 seconds. The PROCESS CYCLE TIME is a. 130 seconds b. 160 seconds c. 120 seconds d. 150 seconds
3- Which of the following reason will make actual output less than effective capacity a. Lunch Breaks for Workers b. Shift Changeover c. Machine Breakdown d. Setup Times
4- A bottleneck operations is the slowest operation in the system which limits the capacity of the system O True O False
5- In an organization, which will have the smallest value a. Design capacity b. Effective Capacity c. Practical Capacity d. Actual Capacity (Actual Output)