Question: 1 . ) UNIT 1 - CHALLENGE 1 . 2 : Defining an Which of the following activities is part of gathering stakeholder expectations? a

1.) UNIT 1- CHALLENGE 1.2: Defining an
Which of the following activities is part of gathering stakeholder expectations?
a.) Transcribing the interview data verbatim into the project scope
b.) Disregarding the stakeholders whose expectations seem out of line with the project scope
c.) Classifying and categorizing the information in order to come up with key expectations
d.) Focusing only on one stated expectation of each stakeholder