Question: 1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20

1. Use the data to calculate the earned value for
1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20 25 % Comp 10 6 100% 12 6 75% 4 5 5 6 5% Conceptual Design Graphics Design Copyright Samples Tooling Production 4 N 25% 6 9 4 10% 6 14 10% NN Total 10 18 26 24 Cumulative 10 28 50 76 100 Select one: a. $454,750 b. $38,850 c. $43,250 d. $100,00