Question: 1. Using the data above, what is the IRR for project Alpha? 2. Using the data above, what is the NPV for project Alpha? 3.

1. Using the data above, what is the IRR for project Alpha?
2. Using the data above, what is the NPV for project Alpha?
3. Using the data above, what is the Payback for Alpha?
4. The IRR, NPV, and Payback for project Beta are below. Which project should the manager select and why? Beta IRR 34.5% Beta NPV $93,288 Beta Payback 1.85
o is presented with the following two mutually exclusive projects. The required return for both projects is 19% Year Project Alpha Project Beta 0 $ (136,000) $ (310,000) 1 $ 64,900 $ 145,500 2 $ 82,900 $ 194,000 3 $ 73,900 $ 138,500 4 $ 59,900 $ 124,000