Question: 1. Using the following figure, perform resource leveling (See samples on pages 220-222 in textbook). Assume that each task can be performed independently of the
1. Using the following figure, perform resource leveling (See samples on pages 220-222 in textbook). Assume that each task can be performed independently of the other tasks. 510 pts
(Use the following blank table to assist in answering.)
| Task 1 | (3 workers) | ||||||||||
| Task 2 | (1 worker) | ||||||||||
| Task 3 | (3 workers) | ||||||||||
| Task 4 | (1 worker) | ||||||||||
| Task 5 | (2 workers) | ||||||||||
| Task 6 | (2 workers) | ||||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
| Workers |
2. Using the same figure as in #1 (listed again below), perform resource-limited scheduling (See samples on pages 222-226 in textbook). Assume that you have only three (3) workers available at any given time. Use slack to determine priority (as per the example in the text in Chapter 6) (50 pts). MUST SHOW ITERATIONS TO GET FULL CREDIT (Similar to Figures 6.10, 6.11, 6.12, 6.13)
| Task 1 | (3 workers) | 3 | |||||||||
| Task 2 | (1 worker) | 1 | |||||||||
| Task 3 | (3 workers) | 3 | |||||||||
| Task 4 | (1 worker) | 1 | |||||||||
| Task 5 | (2 workers) | 2 | |||||||||
| Task 6 | (2 workers) | 2 | |||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
| Workers | 3 | 3 | 3 | 2 | 2 | 3 | 6 | 9 | 6 | 3 |
(Use the following blank table to assist in answering.)
Iteration 1
| Slack | |||||||||||||||||||||
| Task 1 | |||||||||||||||||||||
| Task 2 | |||||||||||||||||||||
| Task 3 | |||||||||||||||||||||
| Task 4 | |||||||||||||||||||||
| Task 5 | |||||||||||||||||||||
| Task 6 | |||||||||||||||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | |
| Workers |
Iteration 2
| Slack | |||||||||||||||||||||
| Task 1 | |||||||||||||||||||||
| Task 2 | |||||||||||||||||||||
| Task 3 | |||||||||||||||||||||
| Task 4 | |||||||||||||||||||||
| Task 5 | |||||||||||||||||||||
| Task 6 | |||||||||||||||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | |
| Workers |
Iteration 3
| Slack | |||||||||||||||||||||
| Task 1 | |||||||||||||||||||||
| Task 2 | |||||||||||||||||||||
| Task 3 | |||||||||||||||||||||
| Task 4 | |||||||||||||||||||||
| Task 5 | |||||||||||||||||||||
| Task 6 | |||||||||||||||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | |
| Workers |
Iteration 4
| Slack | |||||||||||||||||||||
| Task 1 | |||||||||||||||||||||
| Task 2 | |||||||||||||||||||||
| Task 3 | |||||||||||||||||||||
| Task 4 | |||||||||||||||||||||
| Task 5 | |||||||||||||||||||||
| Task 6 | |||||||||||||||||||||
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | |
| Workers |