Question: 1. Using the following network diagram and table what is the slack time for node or activity F. B 1 D 7 G 4 E

1. Using the following network diagram and table

1. Using the following network diagram and table what is the slack time for node or activity "F." B 1 D 7 G 4 E 3 3 F 6 Earliest Finish Activity Time 2 1 3 7 3 Earliest Start 0 2 2 3 5 5 11 Latest Start 0 3 2 Latest Finish 2 4 5 Activity A B C D E F G 3 5 Slack 0 1 0 1 1 10 8 11 15 11 11 11 15 5 11 0 4 2. Using the information from the table you just completed answer the following question? a.) What is the earliest finish time for activity A? b.) What is the latest start time for activity E? c.) What is the activity time for activity F? d.) Which one of the following is the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!