Question: 1 . Using the network diagram only , find a . Shortest task first b . Minimum slack first c . Most critical followers d

1. Using the network diagram only , find
a. Shortest task first
b. Minimum slack first
c. Most critical followers
d. Most successors
2. Using the network diagram and the additional information below, find
a. The crash cost per day
b. Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed.
3. Reconsider Question 2 above, assuming a fixed overhead cost of $30 per day but no project deadline. What is the leastcost crash program? What if the overhead cost was
$40? What if it was $60?\table[[Activity,Crash Time (days),Crashed Cost (total),Normal Time (days),Normal Cost],[A,3,$500,4,$300],[B,1,325,3,250],[C,4,550,7,400],[D,3,250,5,150]]
 1. Using the network diagram only , find a. Shortest task

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!