Question: 1. Using the network diagram only , find Shortest task first Minimum slack first Most critical followers Most successors 2. Using the network diagram and

1. Using the network diagram only , find
Shortest task first
Minimum slack first
Most critical followers
Most successors
2. Using the network diagram and the additional information below, find
The crash cost per day
Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed.
3. Reconsider Question 2 above, assuming a fixed overhead cost of $30 per day but no project deadline. What is the leastcost crash program? What if the overhead cost was $40? What if it was $60?
\begin{tabular}{|l|c|c|c|c|} \hline Activity & Crash Time (days) & Crashed Cost (total) & Normal Time (days) & Normal Cost \\ \hline A & 3 & $500 & 4 & $300 \\ \hline B & 1 & 325 & 3 & 250 \\ \hline C & 4 & 550 & 7 & 400 \\ \hline D & 3 & 250 & 5 & 150 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
