Question: 1. Using the project information below, draw the AON diagram and complete forward and backward pass. Calculate the slack and identify the critical path. (10

1. Using the project information below, draw the
1. Using the project information below, draw the AON diagram and complete forward and backward pass. Calculate the slack and identify the critical path. (10 points) Activity B D E F G Duration 5 3 1 7 4 2 1 Network relationships A-D Finish to Start A-C Finish to Start A-B Start to Start - Lag 2 time units D-E Start to Start - Lag 5 time units D-E Finish to Finish - Lag 1 time unit B-E Finish to Start C-F Finish to Start - Lag 5 time units E-F Finish to Start F-G Finish to Start