Question: 1) Using the Work break structure provided below, calculate the expected task times, perform CPM, and compute the standard deviation of project time. begin{tabular}{|c|c|c|c|c|} hline

1) Using the Work break structure provided below, calculate the expected task times, perform CPM, and compute the standard deviation of project time.

1) Using the Work break structure provided below,

\begin{tabular}{|c|c|c|c|c|} \hline Task & Predecessor & Most likely & Optimistic & Pessimistic \\ \hline A & & 3 days & 2 & 4 \\ \hline B & A & 10 days & 8 & 18 \\ \hline C & A & 5 days & 3 & 10 \\ \hline D & B & 3 days & 3 & 6 \\ \hline E & B,C & 15 days & 13 & 17 \\ \hline F & D & 8 days & 4 & 10 \\ \hline \end{tabular}