Question: 1. what can you do if you find your progress of project development doesn't meet the expectations? 2. please calculate PV, EV, AC, CV, CPI,
1. what can you do if you find your progress of project development doesn't meet the expectations?
2. please calculate PV, EV, AC, CV, CPI, SV, SPI. BAC, ETC, and EAC at Stage 5
3. How much money will you save/ overspend compared to your budget?
| At the End of | Stage | Estimated Cost | Cumulative Estimate | Estimated Duration | Stage Completed (Stage 1) | Stage Completed (Stage 2) | Stage Completed (Stage 3) | Stage Completed (Stage 4) | Stage Completed (Stage 5) | Actual Cost of Stage to Date | Actual Cost of Project to Date |
| Month 1 | Stage 1 | $6,500 | 1 Month | 100% | Not Yet | Not Yet | Not Yet | Not Yet | $6,450 | ||
| Month 2 | Stage 2 | $2,500 | 1 Month | 100% | 100% | Not Yet | Not Yet | Not Yet | $2,500 | ||
| Month 3 | Stage 3 | $2,500 | 1 Month | 100% | 100% | 60% | Not Yet | Not Yet | $2,800 | ||
| Month 4 | Stage 4 | $3,000 | 1 Month | 100% | 100% | 100% | 30% | Not Yet | $3,200 | ||
| Month 5 | Stage 5 | $1,500 |
Step by Step Solution
There are 3 Steps involved in it
1what can you do if you find your progress of project development doesnt meet the expectations A project becomes a failure when it does not deliver what was required within the agreedupon budget and t... View full answer
Get step-by-step solutions from verified subject matter experts