Question: 1. what can you do if you find your progress of project development doesn't meet the expectations? 2. please calculate PV, EV, AC, CV, CPI,

1. what can you do if you find your progress of project development doesn't meet the expectations?

2. please calculate PV, EV, AC, CV, CPI, SV, SPI. BAC, ETC, and EAC at Stage 5

3. How much money will you save/ overspend compared to your budget?

At the End ofStageEstimated CostCumulative EstimateEstimated DurationStage Completed (Stage 1)Stage Completed (Stage 2)Stage Completed (Stage 3)Stage Completed (Stage 4)Stage Completed (Stage 5)Actual Cost of Stage to DateActual Cost of Project to Date
Month 1Stage 1$6,5001 Month100%Not YetNot YetNot YetNot Yet$6,450
Month 2Stage 2$2,5001 Month100%100%Not YetNot YetNot Yet$2,500
Month 3Stage 3$2,5001 Month100%100%60%Not YetNot Yet$2,800
Month 4Stage 4$3,0001 Month100%100%100%30%Not Yet$3,200
Month 5Stage 5$1,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1what can you do if you find your progress of project development doesnt meet the expectations A project becomes a failure when it does not deliver what was required within the agreedupon budget and t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!