Question: 1 . What is a quality audit? ( a ) A team meeting dedicated to measuring and examinations ( b ) A quality based inspection
What is a quality audit?
a A team meeting dedicated to measuring and examinations
b A quality based inspection of work results
c A structured review of quality management activities
Which statement is true about the RACI chart?
a RACI stands for: Responsible, Accountant, Consult, and Inform
b RACI is an example of responsibility assignment matrix
c RACI charts connect risks to the risk owner
A program is a group of
a related projects
b unrelated projects
c A and B
Quality audits:
a Are unnecessary if you do it right the first time
b Must be performed daily for each process
c Are necessary for validation that the quality policy is being followed
and adhered to
The customer wants to make a major change in the project scope when the
project is mostly complete. The project manager should:
a Make the change
b Inform the customer of the impact of the change
c Refuse the change
The following strategies can be used for negative risks
a Exploit, transfer, avoid
b Transfer, avoid, mitigate
c Avoid, mitigate, exploit
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock