Question: 1 . What is the critical path duration? 2 . How long will this project take to complete? 3 . What is the critical path
What is the critical path duration?
How long will this project take to complete?
What is the critical path if activity C takes days to complete?
What is the Critical Path if activity B takes days to complete?
What is the Critical Path if activity J takes days to complete?
Do a CPM Analysis Forward Pass and Backward
Pass on the Network Diagram you created
Answer the following questions. Assume the time units are expressed in days.
What is the total duration of the project?
What is the Total SlackFloat
What is the Free Float?
What activities are Bottlenecks?
What changes would you suggest to optimize the network after the first CPM
analysis?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
