Question: 1 . What is the critical path ( list all the activities on the path ) ? How long is the critical path ( duration

1. What is the critical path (list all the activities on the path)? How long is the critical path (duration)?(5 points)
2. List the activities that have free float and the numbers of the free float. (5 points)
3. What is the duration of activity G?(hint: look at its dependencies)(5 points)