Question: table [ [ Iask , 3 ] , [ A , 2 ] , [ B , 3 ] , [ C , 2
tableIaskABCDEFH
a What is the critical path list all the activities on the path How long is the critical path duration poin b List the activities that have free float and the numbers of the free float. points What is the duration of activity hint: look at its dependencies points