Question: 1) what is the last start (ls) time for activity c? 2) what is the slack for activity d? 3) what is the slack for

1) what is the last start (ls) time for activity c?
2) what is the slack for activity d?
3) what is the slack for activity e?
4) what is slack for activity g?
5) what is the length of the critical path for the project to install a new server at the Northland pines highschool?
Activity Activity Time (days) Immediate Predecessor(s) Task A 2 Task B | 4 4 Task C 1 1 Task D 2 Task E 6 Task F 8 8 B, C Task G3 D, E Task H 5 Task. 4 Task J 5 G, HStep by Step Solution