Question: 1) What is the normal project duration? What is the crash duration? N: C: 2) What is(are) the activity(ies) crashed on step one? What is
1) What is the normal project duration? What is the crash duration? N: C:
2) What is(are) the activity(ies) crashed on step one? What is the additional cost?
3) What is(are) the activity(ies) crashed on step two? What is the additional cost?
4) What is(are) the activity(ies) crashed on step three? What is the additional cost?
5) What is(are) the activity(ies) crashed on step four? What is the additional cost?
6) What is(are) the activity(ies) crashed on step five? What is the additional cost?
Problem 2: Crash the network below to its minimum duration at the lowest cost. FF4 FS2 SS4 FS4 SS4 FF10 FS2 Activity |Total Cost MinimumCrash cost Activity Total CostMinimum Crash cost duration |per day ation per day duration per day $5,000 $12,5003 $8,0003 $15,0003 $18,0005 $18,000 4 $3,000 $15,0003 $2,900 $4,250 $4,500F $3,750 G $4,250H $2,700 1) What is the normal project duration? What is the crash duration? N 2) What is(are) the activity(ies) crashed on step one? What is the additional cost? 3) What is(are) the activity(ies) crashed on step two? What is the additional cost? 4) What is(are) the activity(es) crashed on step three? What is the additional cost? 5) What is(are) the activity(ies) crashed on step four? What is the additional cost? 6) What is(are) the activity(ies) crashed on step five? What is the additional cost