Question: Homework Content Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach

Homework Content
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.
Note: The correct normal project duration, critical path, and total direct cost are provided.
Please Use the table below for reference:
Note: Slope is defined as the cost to crash an activity by 1 day. The maximum crash time is not the same as Crash Duration.
Activity
Predecessor
Normal Duration
(days)
Normal Cost
Crash Duration
(days)
Crash Cost
Slope (Cost to crash the activity by 1 day)
a
-
2
$150
1
$250
$100
b
a
3
$100
2
$180
$80
c
b
2
$200
1
$260
$60
d
b
5
$200
4
$240
$40
e
a
5
$200
3
$280
$40
f
c
3
$150
1
$230
$40
g
d
5
$200
4
$220
$20
h
e, f, g
1
$200
---
---
---
crashing21000_resize_h436_w400.PNG
Question 1
0.5
Points
What is the cost to crash Activity D by one day?
$100
$40
$70
$50
Question 2
0.5
Points
E can be crashed to a maximum of _______ Days
2
1
3
0
Question 3
0.5
Points
What is the cost to crash the project to 14 days?
$1460
$1420
$1400
$1540
Question 4
0.5
Points
What is the maximum crash duration of the project?
14 days
13 days
11 days
12 days
Question 5
1
Point
What is the cost to crash the project to 12 days?
$1400
$1540
$1640
$1460
Question 6
1
Point
Use the file upload question to include a file with the workings/calculations for this crashing assignment.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!