Question: 1) what is the probability that the project will take more than 37 weeks? Activity A B C D E 0 0 C XL-ITMU0 Optimistic

1) what is the probability that the project will take more than 37 weeks?
1) what is the probability that the project will
Activity A B C D E 0 0 C XL-ITMU0 Optimistic 8 6 6 1 8 5 1 1 2 3 2 Time Estimates (weeks) Most Likely Pessimistic Immediate Predecessor(s) 10 11 START 8 18 START 8 10 START 2 3 B 10 13 A, C 6 8 D, E 3 4 DE 5 7 F G 4 5 5 9 2 2 NON UII