Question: 1. With reference to the table below, with a list of activities of a project: Activity Duration (days) Preceding Activities A 5 B 3 A

1. With reference to the table below, with a list

1. With reference to the table below, with a list of activities of a project: Activity Duration (days) Preceding Activities A 5 B 3 A 2 A D 2 B,C E 6 B F 1 D G 3 D a. Draw the Activity-on-Node network diagram, including the Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack for each activity. (8 marks) b. Identify the activities that are on the critical path (1.5 marks), and the duration of the project. (0.5 mark)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!