QUESTION : Please do it only If you are confident, Wrong solution will be reported.

The following table provides information about a particular project:

Activity

Duration (Days)

Preceding

Activity

A

5

_

B

6

_

C

4

A

D

3

A

E

1

A

F

4

E

G

14

D,E

H

12

B,C

I

2

G,H

  1. Represent the project by means of a simple network diagram.
  2. Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.
  3. Identify the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!