Question: QUESTION : Please do it only If you are confident, Wrong solution will be reported. The following table provides information about a particular project: Activity
QUESTION : Please do it only If you are confident, Wrong solution will be reported.
The following table provides information about a particular project:
| Activity | Duration (Days) | Preceding |
| Activity | ||
| A | 5 | _ |
| B | 6 | _ |
| C | 4 | A |
| D | 3 | A |
| E | 1 | A |
| F | 4 | E |
| G | 14 | D,E |
| H | 12 | B,C |
| I | 2 | G,H |
- Represent the project by means of a simple network diagram.
- Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.
- Identify the critical path.